(18C) Priority Scheduling Rule
|
11-27-2018, 02:35 PM
(This post was last modified: 11-27-2018 02:39 PM by SlideRule.)
Post: #1
|
|||
|
|||
(18C) Priority Scheduling Rule
extract from the Working with your Business Consultant Professional Calculator series,
Manufacturing Consultant … formula PRIORITY=(WKHRS-TIME)÷#OPS where WKHRS = work hours until delivery date TIME = total processing time #OPS = number of remaining operations Priority scheduling rules are used to determine the order in which customer orders should be worked. One priority rule uses an index based on the number of work hours until the delivery date, the processing time for the order and the number of operations remaining to complete the order. The lower the index, the higher the priority. SlideRule |
|||
« Next Oldest | Next Newest »
|
Messages In This Thread |
(18C) Priority Scheduling Rule - SlideRule - 11-27-2018 02:35 PM
|
User(s) browsing this thread: 1 Guest(s)