The Hotel Steinenschanze should have become the cantonal data center a little over 10 years ago. At that time it was an hour hotel and was bought by the city. At that time I planned the spatial planning and the interior design of the data center but unfortunately the project was then rejected by the parliament for further consideration (not rejected). The rejection by the parliament cost the then head his job and the project was not pursued any further. Instead of an own data center, two locations were rented (at three times the price of an in-house operation). In return, the government no longer had to go to the palrlament and could increase the running budget instead of the investment.
The old hotel was sold again and demolished and a new beautiful one was rebuilt. This is the story of the building. Hans-Peter |
|||